TMR – Greenvale – 98C Gregory Development Road
Charters Towers Regional Council
Project Manager for 16 km road widening, works include pavement in situ stabilisation, fifteen (15) culvert reconstruction ranging from 1200 x 300 to 2700 x 2400 up to twelve (12) barrels wide, PMB sealing 10 mm primer seal being built by Charters Towers Regional Council construction workforce under PDM management.
- Carried out site construction and project management for all works on this TMR construction project as the council’s management team for the works
- Interpret plans and estimate costs and quantities of concrete precast culverts needed for the project
- Assist with the planning of construction methods and procedures and coordinate the supply of labour and materials
- Interpret regulations / codes of practice to direct the progress of work in line with construction schedules
- Identify inefficiencies in resources, design, or methods to drive productivity
- Completed all tasks in compliance with DTMR specification or statutory obligations (Cultural Heritage and Environmental Management)